Our company has made tremendous progress in the past years.  We have streamlined our operations, cleaned our books of accounts, and updated the Company as per prevailing legal and compliance requirements. To cap it all off, we were able to conduct a fair process to elect the Directors for the next coming years. 

Dhan Bahadur Shrestha
(Chairperson)

Team Members

PROJECT PROGRESS

Desander (Settling Basin)

Settling basin foundation and shear wall reinforcement as well as concreting work progress is around 80%. Remaining works in desander will be finalized during rainy season.Total budget of this section including Head pond according to BOQ is Rs 3,77,45,682/-….

Approach Canal, Gravel Trap

For the construction of remaining approach canal and bell mouth, gravel trap, spill way canal at intake, the excavation work is done. Reinforcement and concreting work for this section will be executed during monsoon….

Weir, under sluice and Intake

Till the end of May 2017, Earth work excavation for the foundation of under sluice and flood wall is completed, about 90% of civil works including foundation and shear wall reinforcement as well as concreting works at under sluice portion is completed. Total budget of this section according to BOQ is Rs6,34,92,810/-….